Here is the work in progress picture gallery

Building status:
18 April 2005
FIRST WORSHIP SERVICE
AT NEW BUILDING
Building status:
17 April 2005
(Cleaning up before laying carpet
in main hall and fitting kitchen).
Building status:
2 April 2005
(All the last odds and ends left to do).
Building status:
30 March 2005
(striping old wallpaper, cleaning, filling holes, checking cealing grid etc...).
Building status:
28 March 2005
(Final touch ups before painting).
Building status:
10 March 2005
(Ladies group comes to give a hand- tearing off old wallpaper & cleaning-up).
Building status:
5 March 2005
(Building dry wall for stage area).
Building status:
26 February 2005
(intalling roof drain
& dry wall of Prayer room).
Building status:
10 February 2005
(building up walls of prayer room
and Stage).

Building status:
29 January 2005
(Clearing up & Removing flooring).

Building status:
22 January 2005
(tearing walls down).

Building status:
01 January 2005
(worshiping and Claiming the building).